The Aquatic Centre is currently under construction. It is tentatively planned to reopen in 2020. Use the Subscribe button at the bottom of the page to get notifications about the project.

View an animated video of the interior design and the exterior design.

Aquatic Programs

Aquatic Renovation and Expansion Project Updates

Project Update - November 15, 2018

During the early planning stages of the Pool Expansion and Renovation project, the Architect / Engineers responsible for the design performed a visual inspection of the building and determined that it was in reasonably good condition besides needing some minor roof repairs. A hazardous material assessment was also performed and indicated that there was some lead paint and asbestos in certain areas but the removal of this was budgeted.

However during the interior demolition phase, Clark Builders discovered that some of the previously hidden structural steel brackets and wooden roof beams had deteriorated. They also discovered additional areas where hazardous materials would need to be addressed. These findings have resulted in the need for further inspection, testing, and repair work.

At this point, the schedule and cost impacts are unknown until further inspection. Council called a Special Meeting on November 14, 2018 to approve an additional $500,000 of contingency funds to ensure there is enough approved budget to take care of the testing and temporary structural support. Fortunately, initial test results show the main concerns are two specific metal support brackets and one wooden beam. Approximately 2/3 of the beams and supports have already been tested.

Presently all exterior work is on schedule and steel structure installation has begun. However, the exterior work timeline will be dependent on the findings of the interior studies.

Project Update - September 24, 2018
The final design includes:
  • An addition to the existing building which will have an 8 lane 25m competition pool (lane pool) that will be deep enough for swimmers to dive in from the pool deck in the shallow end and from dive blocks in the deep end (10ft)
  • A brand new water slide that ends in a runway trough, rather than into the pool which is much safer for slide users and for swimmers
  • An in-ground 20 person hot tub
  • Two meeting/party rooms that have access right from the pool deck and to outside
  • A brand new outdoor water splash park to the immediate south side of the new addition.
  • A brand new leisure pool tank with lazy river and very shallow tots play area with play and spray feature along with a mid-size teach pool that will be about .7 to .9 m deep.
  • Fully updated change rooms with new tile, paint, fixtures, seating and showers
  • A fully family change room converted from the old meeting space and small family change room 
  • A large welcoming front desk, new tile and paint  in the front lobby
  • Larger staff change rooms

 

Aquatic Centre Renovation

 

Aquatic Centre Renovation

 

Aquatic Centre Renovation

 

Aquatic Centre Renovation

 

Project Update - September 5, 2018

Aquatic Centre Renovation

 

Aquatic Centre Renovation

Project Update - August 14, 2018
Aquatic Centre Renovation
Project Update - July 31, 2018
Aquatic Centre Renovation
Project Update - June 8, 2018
Aquatic Centre Renovation
Project Update - May 23, 2018: Aquatic Centre Renovation has been Approved!
We are excited to announce that the 2018 / 2019 Camrose Aquatic Centre Revitalization Plan has been approved!
With a total budget of $17,233,000, the plan includes the following:
  • An addition to the existing aquatic centre to the west.
  • An eight lane 25 m training / fitness pool with a depth of 1.2 m at the shallow end and 3 m at the deep end. This will include competitive diving blocks with sliding rails, a recreational diving board, integrated steps for easy access, and anchors for future play features. This pool will be kept slightly cooler, at around 28 to 28.5 degrees Celsius, compared to the existing pool, which is kept between 29 to 29.5 degrees Celsius.
  • A shallow pool at approximately 1 m deep that will be kept around 31 to 32 degrees Celsius and with easy access entry for water therapy and education.
  • A lazy river also kept at approximately 31 to 32 degrees Celsius.
  • A tots shallow play area with play and splash features that will also be kept at 31 to 32 degrees Celsius.
  • A new water slide that exits into a trough for fun and safe use.
  • An accessible in ground hot tub.
  • Upgrades to the existing change room facilities, including a major expansion to the Family change room. This will provide additional changing space during peak hours as well.
  • Renovations to the front lobby area to provide easier access to the front counter.
  • New heating, air conditioning and ventilation systems.
  • New pool filtration and water treatment systems for all the pools.
  • A steam room.
  • Upgraded fire and security alarm systems.
  • General cosmetic upgrades to the existing lobby and hall areas.
  • A new splash park on the South side of the new addition.
Construction will begin (as soon as permits are approved) with exterior work on the west side of the building during the summer of 2018 while the existing pool remains open to the public. Then in early fall of 2018 the entire facility will be closed for approximately 14 months while the remaining construction takes place. With this approval, we will be exploring fundraising and grant options to help offset the costs if feasible.
We would like to sincerely thank all the supporters who contributed to the design, from the seniors drop in groups, the swim club, syncro club, triathlon club, Special Olympics, lifesaving group, and all of the public.
Project Update - March 26, 2018

Clark Builders and BR2 Architecture provided Administration with some proposed phasing options which included cost options for the Aquatic Centre Project which were then taken to Council on February 20, 2018.


No concepts or decisions on budget have been made, but currently the options are:


Option 1

  • A full-phased with a minimal shut down
  • Total time of 26 months
  • Approximate cost of $18.1M
Option 2
    A full shut down
  • Total time of 15 months
  • Approximate cost of $16.6M
Option 3
  • A partial shut down
  • Total time of 18 months with a 12 month closure
  • Approximate cost of $16.9M
Watch the interior design rendering video. THIS IS ONLY A PRELIMINARY DESIGN. NO CONCEPTS HAVE BEEN APPROVED.
Project Update - January 19, 2018

BR2 Architecture (the designers) and the construction firm Clark Builders are finishing up the final touches on the design based on all of the feedback received from many sources.

Once that is complete, the next step will be to go to Council for approval before we move forward.

Stay tuned!

Project Update - December 6, 2017
The Request for Proposal for the Construction Management of the Pool Expansion Project closed November 24. Ten submissions received which are presently being reviewed.
Wawanesa makes donation to the Aquatic Centre Renovation & Expansion Project

Wawanesa generously donated $30,000 towards our Aquatic Centre Renovation and Expansion Project.

Wawanesa Cheque Presentation to Aquatic Centre

Pictured from left to right are: Darren Daniels from Central Agencies, Cynthia Hunter from Wawanesa, Aquatic Supervisor Marcia Peek, Recreation Facilities Director Dawn Phillips, and Mayor Norm Mayer.

Project Update - September 19, 2017

Last week City staff met with the project architects (BR2) to review the latest concept. These were the highlights:

  • The importance of keeping pool services open as long as possible - the idea is to keep the pool open while the expansion is being built and when that is finished, close off the old pool to complete more construction, and then when everything is finished, open the newly renovated building completely (if possible)
  • The spray park has been closed until 2019 when the structure is rebuilt (in a different location and using some of the refurbished original structures)
  • Discussions regarding the maintenance and upkeep for a sauna versus a steam room
  • The need to resurface the whole roof
  • Discussions around which water filters to use
  • Discussions around the possibility of Camrose County contributing some funding
  • Construction is tentatively scheduled to begin in April 2018
  • We will have a design to share with the public before the end of this year

Our next step is to get detailed pricing on the most recent concept from BR2 (which should be within the next few weeks) and then we will go from there.

Pool Reno Survey Results are in!
The City developed an online survey that was shared with citizens between April 12, 2017 and July 17, 2017 to allow them to provide their feedback about the pool renovations. View the pool survey results.
Project Update - August 10, 2017

City staff met with the architects for renovation design (a company called BR2) to discuss the latest rendering. It was decided that the next step will be to do a mechanical audit to figure out what machinery can be used in the renovated building.

The updated design will also be taken to user groups (the swim clubs), lifeguards and operations staff, maintenance staff, and Council to get their feedback on the practicality of the design.

Phone icon

Contact Us