We are always striving to make the city a better place for our residents and our visitors. Here you will find information and updates to current projects.

2024 Major Construction Projects

More information coming soon!

Sign up to receive road closure notifications.

Municipal Development Plan (MDP)

View more information about the Municipal Development Plan (MDP).

Rudy Swanson Park North Reservoir Roof Replacement

Project Details
The City of Camrose is replacing the structure on top of an existing drinking water reservoir, located within Rudy Swanson Park. The existing reservoir was constructed in 1983. The roof structure (including waterproofing membrane) is original to the facility, and is approaching the end of its useful life. This project will include the removal of the existing roof structure and membrane, and the installation of a new membrane, insulation and roof structure. The project will help protect the City’s treated drinking water supply from potential contamination.

Area Impacted
Construction will take place on the north treated water reservoir, located within the Rudy Swanson Recreational Park, south of 44 Avenue and west of 55 Street.

Tentative Schedule

  • April 8, 2024 – April 20, 2024 – Tree pruning and limited tree removal; install protection measures around remaining trees.
  • April 20, 2024 – Mid-May 2024 – Removal of existing roof structure, including basketball hoops, fencing, lighting, etc.
  • Mid-May 2024 – Mid-July 2024 – Installation of new waterproofing, insulation and roof structure.
  • Mid-July 2024 – Early August 2024 – New chain link fence installation; remove tree protection; reinstate landscaping including sod placement.

Contactor
Vector Construction

What to Expect

Construction Hours and Noise

  • Increased construction traffic and construction noise is anticipated for the duration of the project.
  • Construction activities are generally planned to be from 7:00am to 5:00pm, with the contractor generally working on a schedule of 10 days on and 4 days off (working every second weekend) until the project is complete. The contractor will ensure that no construction activities will happen between 11:00pm and 7:00am, in accordance with the City’s Nuisance Abatement Bylaw.

For more information, please contact our Engineering Department at 780.672.4428 or at engineer@camrose.ca.

Stoney Creek Sinkhole / Storm Sewer Repair

Project Details
In summer 2023, the City of Camrose observed a sink hole developing on the surface above an existing storm sewer within the Stoney Creek ravine slope. Upon further investigation, the storm pipe had suffered a structural failure. The City engaged a contractor to remove the failed pipe and replace with new pipe.

The project involved the excavation, removal and replacement of 130m of storm pipe and three manholes within the Camrose Creek ravine slope.

Area Impacted
Construction happened within the Stoney Creek ravine south of 39 Avenue and east of Parkview Drive.

Proposed Start Date / End Date
The main construction work was completed in the fall of 2023.
(Final restoration work, including trail repaving, will be completed in Spring 2024.)

For more information, please contact our Engineering Department at 780.672.4428 or at engineer@camrose.ca.

Wastewater Treatment Plant Upgrade

View more information about the Wastewater Treatment Plant upgrade.

Our Camrose

At www.ourcamrose.ca you will find other City projects with a variety of engagement opportunities. Click through the projects to learn their details and how you can share your opinion!

Phone icon

Contact Us